In Madhya Pradesh, your town's municipal body or your gram panchayat approves your house plan. This guide explains the routes under the MP Bhumi Vikas Rules, 2012, the documents to keep ready, land diversion, and what you must do after approval.
In Madhya Pradesh, permission to build a house comes from your local body: the municipal corporation, municipal council or nagar parishad in a town, or the gram panchayat in a village. The rules are set out in the MP Bhumi Vikas Rules, 2012, and in towns the application is made online. Before applying, make sure your land papers and land use are in order, and get your plan prepared and signed by a qualified professional. Do not start work until you have permission.
This guide from BHK 99 Real Estate and Constructions explains who approves your plan, the routes available for small residential plots, the documents to keep ready, and what you must do after approval. Rules change, so treat this as a map and confirm the details with your local body before you apply. The rules quoted here are as we read them on 15 November 2026.
"Naksha pass" is not the same as Bhu-Naksha
When people say "naksha pass karana", they mean getting the building plan of the house approved. Bhu-Naksha is something else: it is the digital land map from the revenue records that shows your plot's khasra boundaries. You will need land records for your application, but a Bhu-Naksha printout is not a building permission.
Who approves your house plan
Under rule 2(5)(b) of the MP Bhumi Vikas Rules, the authority that grants permission to construct, alter or demolish a building is the local body for that area:
- In a city or town: the municipal corporation (nagar nigam), municipal council (nagar palika) or nagar parishad. For example, Chhindwara is a municipal corporation and Seoni is a municipal council in the Urban Development and Housing Department's list of urban local bodies.
- In a village: the gram panchayat, under the MP Panchayat Raj Avam Gram Swaraj Adhiniyam, 1993.
Separately, the Directorate of Town and Country Planning gives development permission for developing or sub-dividing land in planning areas. For a family building one house on a plot in an approved layout, the permission you apply for is the building permission from your local body.
Check your land before you draw the plan
Most delays start with land papers, not with the drawing. Check these first:
- Ownership: your registered sale deed, and the khasra map and khatauni from the land records. Rule 16 of the Bhumi Vikas Rules asks for these with the application.
- The layout: if your plot is in a colony, check that the layout is approved. The instant-approval route described below is only for plots in approved layouts.
- Land use: your plot's use must match the town's development plan where one applies. Your architect can check this.
- Diversion of agricultural land: if your plot is still recorded as agricultural land, it has to be diverted to residential use. Since the 2018 amendment of the MP Land Revenue Code, the owner works out and deposits the premium and revised land revenue, then gives written intimation to the Sub-Divisional Officer, and the land is treated as diverted from the date of that intimation (section 59). The same section says this does not by itself permit a change of land use, so the development plan and building permission still apply.
Routes for a house in a town
The online application
Where the local body uses an online system, rule 14 says the application, plans, documents and fees go only through that system, and the permission and plan are digitally signed. The Urban Development and Housing Department links building permission to its online portal, ABPAS (Automated Building Plan Approval System), at abpas.mpurban.gov.in. The portal also offers file tracking, fee calculation from the submitted plan, and online requests for the inspections and certificates described later. Ask your local body whether it accepts applications only on ABPAS.
Instant (deemed) approval for residential plots up to 186 sq m
Rule 12A allows instant or deemed approval for residential plots up to 186 sq m, which ABPAS shows as about 2,000 sq ft. The conditions in the rule are:
- Only an individual plot holder can use it, not a colonizer who plans to sell plots, flats or buildings.
- The plot must be in a layout approved by the Town and Country Planning Department, with development permission from the urban local body.
- The plan must follow the rules and the town's development plan, and be prepared as rule 26 requires.
- You submit the application and an affidavit in the prescribed forms, pay the fees, and indemnify the local body against damage to structural safety and other damage caused by the construction.
- Submitting the forms and affidavit with the fees is itself the sanction. The local body does not inspect or verify documents at that point.
- If the plan or the construction does not follow the rules or the development plan, the approval is cancelled automatically and the illegal construction can be removed.
This route is fast, but it puts the responsibility on you. A mistake in the plan is not caught at the start; it can surface later as a cancelled approval. Use it only with a plan prepared by a qualified professional who has checked open spaces, height and floor area against the rules.
Plots up to 300 sq m: authorised professional or standard plan
Two other routes exist for plots up to 300 sq m:
- An architect or structural engineer with at least 10 years' experience, authorised by the local body, can issue the permission for plots up to 300 sq m (rule 6(3), with rules 26-A and 26-B). They must decide within 30 days. This route is not available to colonizers selling plots.
- In an approved layout, the owner of a plot up to 300 sq m who chooses one of the local body's approved standard plans needs only the fee receipt, which counts as the permission (rule 21(4)).
The regular route
For larger plots, or if you prefer a full check by the local body, you apply in the regular way under rule 14 and the local body's building officer scrutinises the plan before deciding. Rule 29 requires reasons to be given for a refusal.
Documents to keep ready
The exact checklist is the one your local body uses, and ABPAS publishes its own checklists and forms. Under rules 14 to 18, expect to need:
- Proof of ownership: registered sale deed, khasra map and khatauni.
- Approved layout or plot documents, and the diversion intimation and receipt if the land was agricultural.
- Key plan, site plan, building plans and service plans, signed by the owner and by the professional, with the professional's name, qualification and licence number.
- Specifications signed by the professional.
- A supervision certificate from the professional who will supervise the work.
- A certificate that the structural design follows the earthquake-safety requirements of rule 88.
- An authorisation if the applicant is not the owner.
- Fee payment. On ABPAS the fee memo is generated from the submitted plan, so we do not quote amounts here.
Who can sign your house plan
Rule 26 sets out who may prepare and sign plans. An architect registered with the Council of Architecture may sign plans for any building. A licensed structural engineer may sign plans for residential buildings up to 500 sq m and three storeys or 11 m in height. Licensed engineers and supervisors have lower limits; ask your local body how these apply to your plot. Whoever signs, the structural design should come from a qualified structural engineer, because the earthquake-safety certificate is part of your application.
Open spaces, height and floor area
How much of your plot you can build on is controlled by the rules on front, rear and side open spaces (rule 56 for buildings up to 12.5 m high), the floor area ratio for residential use (rule 61, table 8) and your town's development plan. These depend on your plot size, the road width in front and the plan that applies, so ask your architect to show them on your drawing rather than relying on a general rule of thumb.
After you get permission
Permission is the start, not the end. Rule 31 and the rules around it ask the owner to:
- Display the permission at the site and keep the approved drawings there (rule 32).
- Give notice before starting work.
- Give notice when the plinth is ready, so that the building officer can inspect it.
- Give notice when the work is complete.
- Get occupancy permission before anyone lives in the house. The rule says the occupancy certificate is to be issued within 30 days of your request, failing which it is treated as issued.
Rule 33 says the authority inspects within 7 days of a notice and makes the final inspection within 21 days.
How long permission lasts: under rule 23, a sanction is valid for three years. It can be revalidated twice, for one year each time, up to five years in all; after that you must apply afresh. If work begins while the permission is valid, it does not lapse. Applying for revalidation before expiry avoids a fee. The rule for instant approval follows the same period. Check the validity printed on your permission letter, because your local body's own law may also set a time to start work.
Changes during construction: rule 24 does not allow deviations from the sanctioned plan that affect the front open space or parking, among other limits. Get a revised approval before changing the plan on site.
Houses in a gram panchayat area
In a village, section 55 of the MP Panchayat Raj Avam Gram Swaraj Adhiniyam, 1993 says no one may build, alter, add to or reconstruct a building without the gram panchayat's written permission, following its bye-laws. Permission is presumed if the panchayat does not communicate a refusal within 45 days of receiving the application. The panchayat can stop unauthorised work and order it to be altered or demolished.
In practice, ask your gram panchayat secretary for its application form, the documents it needs and its bye-laws, and keep a dated receipt of your application. Even if permission is presumed after 45 days, a written permission is far easier to show later to a bank or a buyer. If your village falls inside a planning area, the plot's use must still match the development plan.
Does RERA apply to my own house?
No, not to a family building a house for its own use. The RERA Act, 2016 requires promoters to register real estate projects developed for sale, and section 3(2) exempts projects on land up to 500 sq m or with up to eight apartments.
Common mistakes
- Starting work on the strength of an application, before permission is in hand.
- Buying an agricultural plot and building without completing the diversion intimation.
- Using the instant route with a plan that breaks open-space or height rules, which can lead to automatic cancellation.
- Changing the plan on site without a revised approval.
- Moving in without occupancy permission. Banks and future buyers often ask for it.
Questions to ask before you apply
- Is my plot in an approved layout, and is its land use residential in the development plan?
- Has the land been diverted, if it was agricultural?
- Which route fits my plot: instant approval, authorised professional, standard plan or regular?
- Who will sign my plans, and what is their registration or licence number?
- Who will give the start, plinth and completion notices, and who will apply for occupancy?
Frequently asked questions
Can I apply for building permission online in Madhya Pradesh?
In towns, yes. The Urban Development and Housing Department's portal for building permission is ABPAS (abpas.mpurban.gov.in). Ask your local body whether it takes applications only online.
What is the 2,000 sq ft instant approval?
It is the instant or deemed approval under rule 12A for residential plots up to 186 sq m (about 2,000 sq ft) in approved layouts. Submitting the forms, affidavit and fees is the sanction, but it is cancelled automatically if the plan or construction breaks the rules.
Do I need permission for repairs?
Rule 12 lists minor works that do not need permission, such as plastering and repairing a roof without changing it. Structural changes, additions and new floors need permission. Check the list with your local body before starting.
How long is building permission valid?
Under rule 23, three years, revalidated up to two more years, five years in all. If work starts within the validity, it does not lapse. Check your permission letter as well.
Is the process the same in Nagpur?
No. Nagpur is in Maharashtra, which has its own regulations. This guide applies only to Madhya Pradesh.
Sources
- Madhya Pradesh Bhumi Vikas Rules, 2012, Directorate of Town and Country Planning, consolidated up to 6 March 2025: rules 2(5), 6(3), 12, 12A, 14–18, 21(4), 23, 24, 26, 26-A, 26-B, 29, 31–33, 56 and 61. The consolidation notes that the gazette text prevails.
- ABPAS, Automated Building Plan Approval System, Urban Development and Housing Department, Madhya Pradesh.
- List of urban local bodies by division, Urban Development and Housing Department, Madhya Pradesh.
- MP Panchayat Raj Avam Gram Swaraj Adhiniyam, 1993, section 55 (copy hosted by PRS Legislative Research).
- MP Land Revenue Code, 1959, with amendments, section 59 as substituted in 2018 (copy hosted by PRS Legislative Research).
- The Real Estate (Regulation and Development) Act, 2016, sections 2(zn) and 3 (copy published by MP RERA).
All sources were read on 15 November 2026.
Get your sanction drawings right the first time
A plan that follows the rules from the start saves months. If you are planning a house in Chhindwara, Seoni or nearby, see our sanction drawings and structural design services, or send your plot papers through our contact page to discuss your plan. When the approval is in place, our guides on which area a per sq ft rate is multiplied by and how to compare quotes help you plan the build.