You do not need to be an engineer to protect your slab. This checklist tells you what to ask the site team to show you before the pour, what IS 456 makes them responsible for, and what happens after the concrete is placed.
You do not need to be an engineer to protect your roof slab, but you do need to ask the right questions before the concrete goes in. The day before the pour, ask the site engineer to show you the approved drawing, the bar bending schedule, the steel and its cover, the shuttering and props, the conduits, the concrete plan, the cube-testing arrangement and the curing plan. If any answer is "we will see later", it is worth waiting.
This guide from BHK 99 Real Estate and Constructions explains what to ask at each of these hold points and why, using IS 456, the Indian code for plain and reinforced concrete. It does not give sizes, mixes or timings, because those must come from your structural drawing and your engineer, not from a general article.
Why the day before the pour matters
Once concrete is placed, it is very difficult and costly to change. IS 456 says that strict supervision is needed during the work, and that it matters most for checking the steel and its position before it is covered up. The code also expects each stage that will be hidden by the next to be inspected as the work goes on.
That is why the hours before a slab pour are your best chance to ask questions. Afterwards, problems can only be found by testing and fixed by repair.
Who is responsible, and what you can ask for
The structural designer decides the slab: its thickness, the steel, the concrete grade, the cover and where construction joints may go. The engineer in charge on site makes sure the work matches the drawing and decides when concrete may be placed and when the shuttering may come off. Your role as owner is to ask to see the checks and keep the records.
Two records are worth asking for by name:
- A pour card, or a written clearance for concrete placement. IS 456 lists pour cards for site organisation and clearance for concrete placement among the records a quality plan should keep.
- Confirmation that the shuttering and props have been checked. The Indian guideline for falsework, IS 14687, says that before concreting the steel and the falsework should have been checked and permission given to start placing concrete.
Hold point 1: drawings and documents
- The structural drawing for this slab, with its revision number. Check that the site is working from the latest one.
- The bar bending schedule. IS 456 says bar bending schedules shall be prepared for all reinforcement. It lists every bar's size, shape, length and number, so you can see what was planned.
- The concrete grade written on the drawing. IS 456 sets M 20 as the lowest grade for reinforced concrete; your drawing states the grade for your building, which may be higher.
- Where construction joints are allowed, if the slab cannot be cast in one go. The code says their position is decided by the designer.
Hold point 2: the steel
- Clean bars, free of loose rust, mud, oil or paint.
- Bars placed and tied as the drawing and schedule show, with crossing bars tied with binding wire so they do not move. Laps should be staggered, not all at one place.
- No welding of crossing bars unless the engineer has allowed it.
- If steel was fixed some days earlier, its position should be checked again just before concreting.
- Cover blocks in place under and beside the bars. The distance between the steel and the concrete surface is called cover. It protects the steel from rusting and from fire. IS 456 sets cover according to the exposure condition and the fire rating, and it is shown on the drawing. Spacers should be the same size as that cover and made of concrete or PVC, and they should not be stacked on top of each other.
- Planks to walk on, so that workers and visitors do not press the top steel down.
Hold point 3: shuttering and props
- The shuttering is firm, level and tight at the joints, so that it does not move or leak slurry during the pour.
- It is clean, with no sawdust, chips or rubbish, and any release oil is on the shuttering, not on the steel.
- Every prop stands on firm ground or on a proper base plate or plank, not on loose soil or a single brick. IS 14687 asks for proper bearing for props and for bracing to make the whole system stable.
- Props and bracing are in place under chhajjas, balconies and other projections too.
- Someone is named to watch the props during the pour, with spare props ready and an agreed signal to stop the pour at once if anything moves. IS 14687 recommends form watchers and a way to stop concreting immediately.
Hold point 4: conduits, boxes and sleeves
Anything that goes inside the slab has to be fixed before the pour:
- Electrical conduits, junction boxes and fan boxes.
- Sleeves for plumbing and drain pipes, and rainwater outlets.
- Any other inserts your design needs.
They should be fixed without cutting or bending the steel out of its drawn position. Take clear photos of the conduit routes before the pour; they help later when someone wants to drill the ceiling.
Hold point 5: the concrete and the pour plan
- Where the concrete comes from: ready-mixed concrete or mixed on site. IS 456 prefers ready-mixed concrete and batching by weight; mixing by volume is allowed only where weighing is not practical.
- How it will be compacted. The code asks for mechanical vibrators, used properly, because both too little and too much vibration harm the concrete.
- No water added on site to make the concrete flow more easily. The code asks for the water-cement ratio to be kept constant. If the concrete is too stiff, the engineer should decide what to do.
- Enough people, equipment and concrete to cast continuously up to the planned joint.
- A weather plan. IS 456 refers hot and cold weather concreting to separate standards, so ask what the site will do on a very hot day or if it rains.
Hold point 6: cube samples and records
Cube tests show whether the concrete that went into your slab reached its specified strength.
- Samples are taken from fresh concrete as per IS 1199, and cubes are made, cured and tested at 28 days as per IS 516.
- The 28-day compressive strength alone decides whether the concrete is accepted. Earlier tests, such as at 7 days, are only an early indication.
- Samples should be taken at random across the pour. The number of samples depends on the volume of concrete, with at least one sample in each shift.
- Each sample should be recorded: date and time, which part of the slab, which batch or truck, and who took it.
Ask for the cube register and the lab reports, and keep copies with your house file.
After the pour: curing and shuttering removal
Curing means keeping the new concrete moist and at a suitable temperature so that it gains strength. IS 456 describes keeping the surface wet by ponding or with wet hessian, or using curing compounds or sheets with the engineer's permission. How long curing must continue depends on the type of cement and the weather, so ask your engineer for the period and who is responsible for it each day.
Shuttering removal is not a matter of counting days alone. IS 456 ties it to the strength the concrete has reached. The guide periods in the code apply only under stated conditions of cement type, temperature and curing, and may need to change otherwise. Ask your engineer when the shuttering and props can come off, and in what order. Some props may need to stay longer to carry the slab's own weight and any loads on it.
While the slab is young, do not let anyone stack bricks, sand or steel on it. After the shuttering is removed, the surface should be inspected and any defects repaired early. If there is any doubt about strength, the code allows core tests and non-destructive tests at the engineer's discretion.
Safety on pour day
A slab pour is busy work at height. Make sure the site has safe access to the slab, edge protection where people work near open sides, and helmets for everyone on site. Keep children and visitors off the slab and away from the area under it while the pour is on. The Bureau of Indian Standards' national building code covers formwork, scaffolding and working at height in detail; in the 2016 edition this was Part 7, Construction Management, Practices and Safety.
Common mistakes and what they cost
- Casting before the steel has been checked: errors in steel are hidden for good once the concrete is placed.
- Cover blocks missing or the wrong size: steel too close to the surface can rust and crack the concrete over the years.
- Props on loose soil: the shuttering can sag or collapse during the pour.
- Water added on site: weaker concrete than the drawing assumes.
- No cube samples: no record of what strength your slab reached.
- Shuttering removed too early: cracks or sagging that need expensive repair.
Questions to ask the site engineer
- Which drawing revision and bar bending schedule are you working from?
- Has the steel been checked, and can I see the pour card or clearance?
- What cover does the drawing show, and are the spacers that size?
- Who checked the props, and who will watch them during the pour?
- Where is the concrete coming from, and how will it be compacted?
- How many cube samples will be taken, and which lab will test them?
- How long will curing continue, and who is responsible each day?
- When will the shuttering and props come off, and in what order?
Frequently asked questions
After how many days can shuttering be removed?
There is no single number. IS 456 links removal to the strength the concrete has gained, and its guide periods apply only under certain conditions. Your engineer decides, based on the cement, the weather, the curing and the slab design.
How many days should a slab be cured?
It depends on the cement type and the weather. Ask your engineer for the period for your slab and keep the surface moist for all of it.
Can water be added if the concrete is too stiff?
Not on the site worker's say. Extra water lowers the strength the design relies on. The engineer should decide how to adjust the mix.
Are cube tests needed for a house?
They are the standard way to confirm the strength of the concrete in your slab, and the 28-day result is what IS 456 uses for acceptance. Ask for them and keep the reports.
What is a pour card?
A short record that the checks before concreting are done and the pour is cleared to start. IS 456 lists it among the records of a quality plan. Ask the site team to fill one in and show it to you.
Sources
- IS 456:2000, Plain and Reinforced Concrete — Code of Practice, Bureau of Indian Standards (public copy, reprint with amendments 1 and 2): clauses 5.6, 6.1, 7, 10, 11, 12, 13, 14.1, 15, 17 and 26.4. Later amendments up to No. 6 exist; check the current text with BIS.
- IS 14687:1999, Falsework for Concrete Structures — Guidelines, Bureau of Indian Standards: clauses 4, 7.10, 9.1, 9.2 and 9.4.
- IS 2502:1963, Code of Practice for Bending and Fixing of Bars for Concrete Reinforcement, Bureau of Indian Standards: clause 7.
- IS 1199 (Part 1):2018, Fresh Concrete — Sampling, and IS 516 (Part 1/Section 1):2021, Hardened Concrete — Testing of Strength, Bureau of Indian Standards.
- National Building Code of India 2016, Part 7, Construction Management, Practices and Safety, Bureau of Indian Standards. The 2016 code has since been replaced by the National Building Construction Standards 2026; check the current part on construction safety.
All sources were read on 15 November 2026.
Talk to us about your slab
If your slab is coming up and you want a second look at the drawing, the steel or the pour plan, send your structural drawing through our contact page. See how RCC structural design sets the slab before the site starts, and if you live away from the site, how remote-owner turnkey projects keep you informed. Our guide on comparing quotes explains how to put cement and steel specifications into your contract.