Labour contract, item-rate or turnkey? The right choice depends on who designs, who buys the materials, who carries price and quantity changes, and how much of your own time you can give. This guide compares them side by side.
There are three common ways to hire someone to build your house. In a labour contract, you buy the materials and the contractor supplies the workers. In an item-rate contract, the contractor supplies materials and labour and is paid for each item of work at an agreed rate on the quantity actually done. In a turnkey contract, one party designs and builds the house for an agreed price. The right choice depends on who designs, who buys materials, who carries price and quantity changes, and how much of your own time you can give.
This guide from BHK 99 Real Estate and Constructions compares the three without pushing any one of them. It explains what you take on in each, how tax and price changes work, and what to write into the agreement whichever you choose.
First, check what the word means in your quote
Names are used loosely on Indian sites. Two things to check before comparing:
- Many "turnkey" quotes are really a per sq ft package for materials and labour, with design not included. True turnkey, which government works call design and build, puts design and construction with one party. Ask whether architectural drawings, structural design and approvals are inside the price.
- A per sq ft package for materials and labour is a fixed price for the work described, worked out by area. Our guide on which area a per sq ft rate is multiplied by explains how to read it.
The Government of India's Manual for Procurement of Works (2025) describes the formal versions of these arrangements: a lump-sum contract with a fixed price for defined work, an item-rate contract paid for measured quantities at quoted rates, and an engineering, procurement and construction contract (also called design and build), where the contractor takes on design and construction for a lump sum. Its comparison of contract types notes that a lump sum gives little room for change, while an item-rate contract allows more change because payment follows the quantities.
Labour contract: you buy the materials
The contractor supplies workers, and sometimes tools, scaffolding and shuttering. You buy cement, steel, sand, aggregate, bricks or blocks, and everything else.
What you take on:
- Buying, delivery, storage and stock checks for every material, on time so that work does not stop.
- Checking quality: brands, grades, ISI marks and delivery records.
- Any rise in material prices during the work, because you are buying at the price of the day.
- Wastage and theft on site.
- Separate design: you hire the architect and structural engineer and get the approvals.
- Supervision: someone with technical knowledge needs to check the work regularly.
It can suit an owner who lives near the site, has time every week, knows local suppliers and has an engineer to supervise. The quoted labour rate looks low because materials are not in it, so compare the full cost, not the labour rate alone.
Write down: what the labour rate covers (tools, scaffolding, shuttering, water, electricity on site, curing), how work is measured for payment, and who orders materials and how much notice they need.
Item-rate contract: paid item by item
The contractor quotes a rate for each item in a bill of quantities: excavation per cubic metre, concrete per cubic metre, steel per kilogram, brickwork, plaster, flooring and so on. You pay for the quantity actually done, measured at site.
What you take on:
- Design and drawings, usually through your own architect and structural engineer, because the bill of quantities comes from the drawings.
- Measurement: someone has to measure the work and check the bills. The Indian standard method for measuring quantities is the IS 1200 series, so agree in the contract which method will be used.
- Quantity changes: if the quantities grow, so does the bill. The works manual notes that reasonable variations in quantities are allowed in item-rate contracts.
What the contractor takes on: buying materials to the agreed specification, their prices for the items quoted (unless the contract has a price-change clause), and workmanship.
It can suit an owner who has complete drawings and wants transparent, item-wise billing, with an engineer or quantity surveyor to check measurements.
Write down: the bill of quantities with specifications, the method of measurement, who measures and signs the joint measurement record, rates for items not in the list, and how price changes are handled.
Turnkey (design and build): one party for the whole job
One party is responsible for designing and building the house to an agreed scope and specification, usually for a lump sum or an agreed per sq ft price. The works manual says this approach transfers design and construction risks to the contractor, while the owner specifies the core requirements.
What you take on:
- Defining what you want clearly: the brief, the scope, and the specification of every main material and finish.
- Approving the design at each stage, and accepting that changes after approval cost more.
- Checking that the work matches what was agreed, through visits, photos and stage inspections.
What the contractor takes on: design coordination, buying materials, labour, site management, and the risk that the work costs them more than they priced, within what the agreement says.
It can suit an owner who lives away from the site, has limited time, or wants one point of responsibility. It depends on a tight written scope; anything left vague can become an extra.
Write down: exactly what design, approval and site services are included, the specification sheet, allowances for items you will choose later, the price-change clause if any, and how changes you ask for are priced.
Who does what, side by side
- Who designs? Labour contract: you, through your architect and engineer. Item-rate: usually you. Turnkey: the turnkey party, to your approved brief.
- Who buys materials? Labour: you. Item-rate: the contractor. Turnkey: the turnkey party.
- Who checks material quality? Labour: you. Item-rate and turnkey: the contractor, with your checks against the specification.
- Who carries quantity changes? Labour: you, through material quantities. Item-rate: you pay for measured quantities. Turnkey: the turnkey party for the agreed scope; you pay for changes you ask for.
- Who carries material price rises? Labour: you. Item-rate and turnkey: the contractor, unless the contract has a price-change clause.
- How much of your time? Labour: the most. Item-rate: moderate, mainly measurement and bills. Turnkey: the least, mainly approvals and checks.
GST: the contract type changes the tax
How GST applies depends on what the contract supplies. The GST exemption list includes pure labour contracts for construction of a single residential unit that is not part of a residential complex. A contract that also supplies materials is taxed. Rules can change and the details matter, such as whether the contractor also supplies some materials or equipment, so ask each contractor to show GST separately and confirm the position with your chartered accountant.
When prices change
Cement and steel prices can move during a build. Who pays depends on the contract:
- In a labour contract, you buy at the price of the day, so you carry the change.
- In an item-rate or turnkey contract, the contractor carries it unless the agreement has a price-change clause.
If there is such a clause, the works manual recommends stating the base date and the formula, so that different quotes can be compared on the same footing. Ask for both in writing.
Three situations, three contracts
Here is how the same events play out under each contract. This is an illustration of who pays, not a price comparison.
- Steel prices rise halfway through the frame. Labour contract: you pay more for the steel you still have to buy. Item-rate or turnkey without a price-change clause: the contractor absorbs it. With a clause: you pay the difference worked out by the agreed formula.
- The structural engineer revises a slab and it needs more steel. Labour contract: you buy more steel and pay the labour for it. Item-rate: you pay for the extra measured quantity. Turnkey: it depends on whether the revision is part of the agreed design scope or a change you asked for, so the agreement should say.
- You choose costlier tiles than planned. Labour contract: you pay the price difference directly. Item-rate: a new rate is agreed for the new item. Turnkey: you pay the difference over the allowance in the agreement.
Which suits you?
Ask yourself four questions:
- How much time can I give the site each week, and do I live nearby?
- Do I have an architect and a structural engineer, and are the drawings complete?
- Do I know where to buy materials, and can I check their quality?
- Do I want a fixed price more than item-by-item control?
If you have time, nearby presence and an engineer, a labour or item-rate contract can work. If you have little time, live elsewhere or want one point of responsibility, turnkey may suit you better. Mixed arrangements are also common, such as a labour contract where you supply only cement and steel, or turnkey with finishes you choose later. Whatever the mix, write down exactly who supplies what.
Write these into any contract
- The scope of work and the drawing set with its revision.
- Who designs, who signs structural drawings and who gets approvals.
- Who supplies which materials, with brands and grades.
- How work is measured and who certifies each bill.
- A payment schedule linked to work actually done. The works manual warns against front-loading, meaning asking for more money early than the work done justifies.
- The price-change clause, if any, with base date and formula.
- How changes you ask for are priced.
- The completion period and what happens on delay.
- How defects noticed during and after the work will be dealt with.
- GST: included, extra, or not applicable.
Our guide on comparing quotes shows how to put two contractors' offers on the same basis.
Common mistakes
- Comparing a labour rate with a turnkey rate as if they covered the same things.
- Calling a materials-and-labour package "turnkey" without checking whether design and approvals are included.
- Choosing a labour contract without the time or the engineer to supervise it.
- An item-rate contract with no agreed method of measurement.
- A turnkey contract with a vague specification, which turns every finish into an extra.
Frequently asked questions
Is a labour contract cheaper?
The quote is lower because it leaves out materials. The real comparison is the total: materials, wastage, your time, supervision and any price rises, against a contract where the contractor carries those. Compare full costs on the same scope before deciding.
Is turnkey the same as a per sq ft package?
Not always. A per sq ft package for materials and labour may not include design or approvals. True turnkey, or design and build, includes design. Ask what is inside the price.
What does a labour contractor usually provide?
It varies. Some provide only workers, others also bring tools, scaffolding and shuttering. Write down exactly what is included.
Can I change the contract type midway?
It is possible but messy. Measure and record all work done and settle accounts first, then sign a fresh agreement for the rest.
Who handles approvals and drawings?
In labour and item-rate contracts, usually you, through your architect and engineer. In turnkey, it depends on the agreement. Our guide to building permission in Madhya Pradesh explains what the approval involves.
Sources
- Manual for Procurement of Works, Second Edition 2025, Department of Expenditure, Ministry of Finance, Government of India: sections 3.2.1 (lump sum), 3.2.2 (item rate), 3.2.5 (engineering, procurement and construction), 3.2.7 (comparison of contract types), 3.2.5 para 17(b) (payment milestones) and 5.4 (price variation).
- CGST Notification 12/2017 (Central Tax Rate), consolidated to 1 April 2019, serial 11. Check later amendments.
- IS 1200 series, Method of measurement of building and civil engineering works, Bureau of Indian Standards (list of parts).
All sources were read on 15 November 2026.